The Stellantis Windsor Assembly Plant volition power betwixt full-production, reduced shifts and afloat shut-downs for the adjacent 12 weeks arsenic car makers proceed to navigate caller marketplace conditions brought connected by U.S. tariffs connected the Canadian car sector.
The institution says the changes are associated with changing exemplary years
CBC News
· Posted: May 06, 2025 9:03 AM EDT | Last Updated: 8 minutes ago
The Stellantis Windsor Assembly Plant volition power betwixt full-production, reduced shifts and afloat shut-downs for the adjacent 12 weeks. This is happening as auto makers proceed to navigate caller marketplace conditions brought connected by U.S. tariffs connected the Canadian car sector.
But a spokesperson for the company did not notation the tariffs successful an email to CBC astir the caller schedule.
Instead, Lou Ann Gosselin said the changes are associated with the changeover successful accumulation year.
"These modifications are indispensable arsenic we implicit the 2025 exemplary year, physique and hole for the motorboat of the 2026 exemplary twelvemonth Chrysler Pacifica, Chrysler Voyager/Grand Caravan and Dodge Charger," Gosselin said.
"We volition proceed to show the situation."
The national representing workers astatine the works has told its members to expect "alternate and fluctuating enactment schedules" for the adjacent 12 weeks.
Unifor Local 444 posted the pursuing docket connected its Facebook page:
- Week of May 12, May 19 and June 30: two shifts running
- Week of May 26, June 9 and June 23: lone Shift One working
- Week of June 2, June 16 and July 7: lone Shift Two working
- Week of July 14: accumulation down
- Weeks of Aug. 18 and 25: Planned summertime shutdown